Evaluation and Improvement of the Main Mining Operations in the Limestone Quarry of Assiut Cement Company, Egypt /
المؤلف
Abdel-Rasoul, Mohamed Elseman Ibrahim.
هيئة الاعداد
باحث / محمد السمان إبراهيم
مشرف / مصطفي محمد الببلاوي
مناقش / محمد عبد التواب الجندي
مناقش / محمد رجائي الطحلاوي
الموضوع
Quarries and quarrying.
تاريخ النشر
2016.
عدد الصفحات
108 P. :
اللغة
الإنجليزية
الدرجة
ماجستير
التخصص
الهندسة (متفرقات)
الناشر
تاريخ الإجازة
28/7/2016
مكان الإجازة
جامعة أسيوط - كلية الهندسة - Mining and Metallurgical Engineering
الفهرس
Only 14 pages are availabe for public view

from 131

from 131

Abstract

Research in the area of mineral resources and mining engineering has significant interest in recent
years. The national economy in Egypt can be very much supported from exploitation of its mineral
resources.
Assiut Cement Company (ACC) is one of the major cement producers in Egypt, producing about
five million tons of cement yearly. This research has been carried out at the limestone quarries of
this company as part of research activities in response to the national interest of research in the
field of mining industry. This study focused on the main operations in surface mining, drilling,
blasting and loading and transportation.
Drilling operation part:
A good distribution and implementation of equipment and machines along the quarry faces is
considered a challenge to the mining engineer or the quarry operator. These equipment cost large
investments in the production processes and need high skill to be efficiently distributed and
operated. In this investigation, study of the optimum distribution of the available drilling machines
of different specifications and capacities along the faces of the lime stone quarry of Assiut Cement
Company has been carried out. A mathematical model has been used to find and analyze several
alternatives and to choose the best alternative. Calculation of the minimum number of drilling
machines that satisfy the annual production plan has carried out to decrease production costs.
Blasting operation part:
This part presents the measurements and analysis of ground vibrations induced by bench blasting
operations in limestone quarry at Assiut Cement Company (CEMEX), in Egypt. The objective of
this vibration analysis, is to establish specific site relationships that can be used to determine safe
explosive quantity per delay for various distances from buildings. For this purpose, blasts have
been recorded using five seismographs to record ground vibrations events. Buildings and
constructions close the quarry area have been given the first priority in these measurements.
Ground vibration components were measured for each blasting event. After carrying out statistical
analysis, the site-specific parameters were determined to predict the peak particle velocity. Also
this analysis establishes prediction curves of maximum charge per delay versus distance for
different damage criteria. These curves enables control of blasting in order not to damage the
nearby buildings, especially plant buildings and structures. The particle velocities and frequency
values of all blast events were evaluated according to German DIN 4150 in order to determine the
damage risks of the nearby structures.
Material handling part:
In the process or manufacturing industry, raw materials and products need to be transported from
one manufacturing stage to another. Material handling equipment are designed such that they
facilitate easy, cheap, fast and safe loading and unloading with least human interference.
Determining the optimum number of haul units for a quarry is a task of critical importance.
Regardless of the size or number of haul units used in a quarry, the hauling system’s total
production can never exceed the productivity of the loading facility. This study presents an
optimized haul unit number based on the excavator characteristics. Belt conveyor system can be
employed for easy handling of materials beyond human capacity in terms of weight and height.
This study discusses the design calculations and considerations of belt conveyor system for
limestone using 3 rolls idlers, in terms of size, capacity and speed to be handled as well as its
maximum loading capacity. That is in order ensure fast, continuous and efficient movement of
crushed limestone while avoiding halt or fatalities during loading and unloading.